DETAIL DESIGN OF T3’’ TRANSPORTATION TUNNEL

DETAIL DESIGN OF T3’’ TRANSPORTATION TUNNEL

Narrative Description of Project:

T37 Tunnel has been designed in the right bank of the
dam for transportation of the machinery.
Intake portal of T37 tunnel starts at bridge #2,
crosses by DT1 and DT2 tunnels and ends at bridge
#3. T3’ tunnel is in the south of T37 and P11 tunnel is
also loca ted in the east, although there is an access
between P11 and T3′ tunnels, named P38 tunnel, T37’
should be another access tunnel to have more
frequent and efficient transportations.

Search

Popular Posts

  • TRANSPORTATION TUNNEL TO UPSTREAM GATE CHAMBER (MTT1) DESIGN
    TRANSPORTATION TUNNEL TO UPSTREAM GATE CHAMBER (MTT1) DESIGN

    For access and transfer of gate and equipment from downstream to the upstream caverns of gate chamber need to excavate a transportation tunnel for MLDT. The tunnel named MTT (middle level diversion transportation tunnel) and will be connected to the ACT1 tunnel. MTT tunnel invert will be located a canal for draining of water to…

  • TRANSPORTATION TUNNEL TO UPSTREAM GATE CHAMBER (MTT) DESIGN
    TRANSPORTATION TUNNEL TO UPSTREAM GATE CHAMBER (MTT) DESIGN

    TRANSPORTATION TUNNEL TO UPSTREAM GATE CHAMBER (MTT) DESIGN NARRATIVE DESCRIPTION OF PROJECT

  • Detail Design of Load Cell Cavern in Transportation Tunnel (T37)
    Detail Design of Load Cell Cavern in Transportation Tunnel (T37)

    DETAIL DESIGN OF LOAD CELL CAVERN IN TRANSPORTATION TUNNEL (T37) NARRATIVE DESCRIPTION OF PROJECT: As a matter of fact, DT1 and DT2 have been designed in Rogun Dam and HPP as diversiontunnels of the Vakhsh River.Intake portals of the mentioned t unnels are located at the left bank (first part) and their outlet portals at…